General Timeline and Process of Alliant's Proposal
May 14, 2008
- Draft Environmental Impact Statement (EIS) was released.
Before June 30, 2008 (45 days following release of draft EIS)
- Public comments accepted at the Public Service Commission (PSC) for 45 days following the release of the draft EIS.
- Tell the PSC you don't want any more dirty coal! Email the PSC before June 30, 2008 to tell them you want clean energy technology for Wisconsin. No more dirty coal!
Late summer 2008
- Final Environmental Impact Statement issued.
- Public hearings will follow the final EIS. Another great time to get involved. Join us at the public hearings by contacting Ryan in our office at rschryver@CleanWisconsin.org or by calling (608) 251-7020 extension 25.
December 2008
- The decision on construction and the location of the plant (Cassville or Portage) will be made by the PSC.